Advertisements
Advertisements
Question
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Advertisements
Solution
Observe that Min (A, B) = 5, corresponds to job VI on machine B and job VII on machine A.
∴ Job VI is placed last and job VII is placed first in sequence.
| VII | VI |
Then the problem reduces to
| Job | I | II | IIII | IV | V |
| Machine A | 7 | 16 | 19 | 10 | 14 |
| Machine B | 12 | 14 | 14 | 10 | 6 |
Now, Min (A, B) = 7, corresponds to job I on machine A.
∴ Job I is placed second in sequence.
| VII | I | VI |
Then the problem reduces to
| Job | II | III | IV | V |
| Machine A | 16 | 19 | 10 | 14 |
| Machine B | 14 | 14 | 10 | 16 |
Now, Min (A, B) = 10, corresponds to job IV on machine A as well as on machine B.
∴ Job IV is placed second last in sequence.
| VII | I | IV | VI |
OR
| VII | I | IV | VI |
Then the problem reduces to
| Job | II | III | V |
| Machine A | 16 | 19 | 14 |
| Machine B | 14 | 14 | 16 |
Now, Min (A, B) = 14, corresponds to job II and job III on machine B and job V on machine A.
∴ These three jobs can be placed in the sequence in order:
V – III – II or V – II – III
∴ The optimal sequence can be
| VII | I | IV | V | III | II | VI |
OR
| VII | I | V | III | II | IV | VI |
OR
| VII | I | IV | V | II | III | VI |
OR
| VII | I | V | II | III | IV | VI |
∴ We consider the optimal sequence as VII – I – IV – V – III – II – VI
Total Elapsed Time
| Job | Machine A | Machine B | ||
| In | Out | In | Out | |
| VII (5, 7) | 0 | 5 | 5 | 12 |
| I (7, 12) | 5 | 12 | 12 | 24 |
| IV (10, 10) | 12 | 22 | 24 | 34 |
| V (14, 16) | 22 | 36 | 36 | 52 |
| III (19, 14) | 36 | 55 | 55 | 69 |
| II (16, 14) | 55 | 71 | 71 | 85 |
| V (15, 5) | 71 | 86 | 86 | 91 |
∴ Total elapsed time = 91 units
Idle time for Machine A = 91 – 86
= 5 units
Idle time for Machine B = 5 + 2 + 3 + 2 + 1
= 13 units
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
| Job | 1 | 2 | 3 | 4 | 5 | 6 |
| Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
| Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
| Job | I | II | III |
| Department A | 8 | 6 | 5 |
| Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Choose the correct alternative :
The objective of sequencing problem is
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours, while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
| Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
| Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
| Job | I | II | III | IV | V |
| Lathe | 4 | 1 | 5 | 2 | 5 |
| Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
| Machines | Jobs (Processing times in minutes) | ||||||
| I | II | III | IV | V | VI | VII | |
| Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
| Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
| Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
| 1 | 13 | 3 | 18 |
| 2 | 18 | 8 | 4 |
| 3 | 8 | 6 | 13 |
| 4 | 23 | 6 | 8 |
Choose the correct alternative:
| Machine | Job | |||
| A | B | C | D | |
| I | 5 | 6 | 8 | 4 |
| II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
Choose the correct alternative:
If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
In assignment problem each worker or machine is ______ capable of handling any job
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
| Book | I | II | III | IV | V |
| Machine A | 4 | 9 | 8 | 6 | 5 |
| Machine B | 5 | 6 | 2 | 3 | 4 |
| Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.
