Advertisements
Advertisements
प्रश्न
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Advertisements
उत्तर
Observe that Min (A, B) = 5, corresponds to job VI on machine B and job VII on machine A.
∴ Job VI is placed last and job VII is placed first in sequence.
| VII | VI |
Then the problem reduces to
| Job | I | II | IIII | IV | V |
| Machine A | 7 | 16 | 19 | 10 | 14 |
| Machine B | 12 | 14 | 14 | 10 | 6 |
Now, Min (A, B) = 7, corresponds to job I on machine A.
∴ Job I is placed second in sequence.
| VII | I | VI |
Then the problem reduces to
| Job | II | III | IV | V |
| Machine A | 16 | 19 | 10 | 14 |
| Machine B | 14 | 14 | 10 | 16 |
Now, Min (A, B) = 10, corresponds to job IV on machine A as well as on machine B.
∴ Job IV is placed second last in sequence.
| VII | I | IV | VI |
OR
| VII | I | IV | VI |
Then the problem reduces to
| Job | II | III | V |
| Machine A | 16 | 19 | 14 |
| Machine B | 14 | 14 | 16 |
Now, Min (A, B) = 14, corresponds to job II and job III on machine B and job V on machine A.
∴ These three jobs can be placed in the sequence in order:
V – III – II or V – II – III
∴ The optimal sequence can be
| VII | I | IV | V | III | II | VI |
OR
| VII | I | V | III | II | IV | VI |
OR
| VII | I | IV | V | II | III | VI |
OR
| VII | I | V | II | III | IV | VI |
∴ We consider the optimal sequence as VII – I – IV – V – III – II – VI
Total Elapsed Time
| Job | Machine A | Machine B | ||
| In | Out | In | Out | |
| VII (5, 7) | 0 | 5 | 5 | 12 |
| I (7, 12) | 5 | 12 | 12 | 24 |
| IV (10, 10) | 12 | 22 | 24 | 34 |
| V (14, 16) | 22 | 36 | 36 | 52 |
| III (19, 14) | 36 | 55 | 55 | 69 |
| II (16, 14) | 55 | 71 | 71 | 85 |
| V (15, 5) | 71 | 86 | 86 | 91 |
∴ Total elapsed time = 91 units
Idle time for Machine A = 91 – 86
= 5 units
Idle time for Machine B = 5 + 2 + 3 + 2 + 1
= 13 units
APPEARS IN
संबंधित प्रश्न
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
| Policy | 1 | 2 | 3 |
| Data Entry | 90 | 120 | 180 |
| Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Choose the correct alternative :
The objective of sequencing problem is
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours, while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.
One machine - one job is not an assumption in solving sequencing problems.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
| Job | I | II | III | IV | V |
| Lathe | 4 | 1 | 5 | 2 | 5 |
| Surface grinder | 3 | 2 | 4 | 3 | 6 |
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
| Type | 1 | 2 | 3 | 4 | 5 |
| Machine A | 16 | 20 | 12 | 14 | 22 |
| Machine B | 10 | 12 | 4 | 6 | 8 |
| Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Choose the correct alternative:
| Machine | Job | |||
| A | B | C | D | |
| I | 5 | 6 | 8 | 4 |
| II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
Choose the correct alternative:
If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
In assignment problem each worker or machine is ______ capable of handling any job
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
| Jobs | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
| Book | I | II | III | IV | V |
| Machine A | 4 | 9 | 8 | 6 | 5 |
| Machine B | 5 | 6 | 2 | 3 | 4 |
| Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.
