Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Advertisements
उत्तर
Observe that Min (A, B) = 5, corresponds to job VI on machine B and job VII on machine A.
∴ Job VI is placed last and job VII is placed first in sequence.
| VII | VI |
Then the problem reduces to
| Job | I | II | IIII | IV | V |
| Machine A | 7 | 16 | 19 | 10 | 14 |
| Machine B | 12 | 14 | 14 | 10 | 6 |
Now, Min (A, B) = 7, corresponds to job I on machine A.
∴ Job I is placed second in sequence.
| VII | I | VI |
Then the problem reduces to
| Job | II | III | IV | V |
| Machine A | 16 | 19 | 10 | 14 |
| Machine B | 14 | 14 | 10 | 16 |
Now, Min (A, B) = 10, corresponds to job IV on machine A as well as on machine B.
∴ Job IV is placed second last in sequence.
| VII | I | IV | VI |
OR
| VII | I | IV | VI |
Then the problem reduces to
| Job | II | III | V |
| Machine A | 16 | 19 | 14 |
| Machine B | 14 | 14 | 16 |
Now, Min (A, B) = 14, corresponds to job II and job III on machine B and job V on machine A.
∴ These three jobs can be placed in the sequence in order:
V – III – II or V – II – III
∴ The optimal sequence can be
| VII | I | IV | V | III | II | VI |
OR
| VII | I | V | III | II | IV | VI |
OR
| VII | I | IV | V | II | III | VI |
OR
| VII | I | V | II | III | IV | VI |
∴ We consider the optimal sequence as VII – I – IV – V – III – II – VI
Total Elapsed Time
| Job | Machine A | Machine B | ||
| In | Out | In | Out | |
| VII (5, 7) | 0 | 5 | 5 | 12 |
| I (7, 12) | 5 | 12 | 12 | 24 |
| IV (10, 10) | 12 | 22 | 24 | 34 |
| V (14, 16) | 22 | 36 | 36 | 52 |
| III (19, 14) | 36 | 55 | 55 | 69 |
| II (16, 14) | 55 | 71 | 71 | 85 |
| V (15, 5) | 71 | 86 | 86 | 91 |
∴ Total elapsed time = 91 units
Idle time for Machine A = 91 – 86
= 5 units
Idle time for Machine B = 5 + 2 + 3 + 2 + 1
= 13 units
APPEARS IN
संबंधित प्रश्न
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
| Job | 1 | 2 | 3 | 4 | 5 | 6 |
| Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
| Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
| Jobs | I | II | III | IV | V | VI | VII |
| Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
| Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
| Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Choose the correct alternative :
The objective of sequencing problem is
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
| Job | I | II | III | IV | V |
| Lathe | 4 | 1 | 5 | 2 | 5 |
| Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
| Machines | Jobs (Processing times in minutes) | ||||||
| I | II | III | IV | V | VI | VII | |
| Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
| Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
| Type | 1 | 2 | 3 | 4 | 5 |
| Machine A | 16 | 20 | 12 | 14 | 22 |
| Machine B | 10 | 12 | 4 | 6 | 8 |
| Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
| Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
| 1 | 13 | 3 | 18 |
| 2 | 18 | 8 | 4 |
| 3 | 8 | 6 | 13 |
| 4 | 23 | 6 | 8 |
Choose the correct alternative:
| Machine | Job | |||
| A | B | C | D | |
| I | 5 | 6 | 8 | 4 |
| II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
In assignment problem each worker or machine is ______ capable of handling any job
______ time is the time when the machine is available but is waiting for a job to be processed
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
| Jobs | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______