Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Advertisements
Advertisements

प्रश्न

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II III IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7
बेरीज
Advertisements

उत्तर

Observe that Min (A, B) = 5, corresponds to job VI on machine B and job VII on machine A.

∴ Job VI is placed last and job VII is placed first in sequence.

VII           VI

Then the problem reduces to

Job I II IIII IV V
Machine A 7 16 19 10 14
Machine B 12 14 14 10 6

Now, Min (A, B) = 7, corresponds to job I on machine A.

∴ Job I is placed second in sequence.

VII I         VI

Then the problem reduces to

Job II III IV V
Machine A 16 19 10 14
Machine B 14 14 10 16

Now, Min (A, B) = 10, corresponds to job IV on machine A as well as on machine B.

∴ Job IV is placed second last in sequence.

VII I IV       VI

             OR

VII I       IV VI

Then the problem reduces to

Job II III V
Machine A 16 19 14
Machine B 14 14 16

Now, Min (A, B) = 14, corresponds to job II and job III on machine B and job V on machine A.

∴ These three jobs can be placed in the sequence in order:

 V – III – II or V – II – III

∴ The optimal sequence can be

VII I IV V III II VI

              OR

VII I V III II IV VI

              OR

VII I IV V II III VI

              OR

VII I V II III IV VI

∴ We consider the optimal sequence as VII – I – IV – V – III – II – VI

Total Elapsed Time

Job Machine A Machine B
In Out In Out
VII (5, 7) 0 5 5 12
I (7, 12) 5 12 12 24
 IV (10, 10) 12 22 24 34
V (14, 16) 22 36 36 52
III (19, 14) 36 55 55 69
II (16, 14) 55 71 71 85
V (15, 5) 71 86 86 91

∴ Total elapsed time = 91 units

Idle time for Machine A = 91 – 86

= 5 units

Idle time for Machine B = 5 + 2 + 3 + 2 + 1

= 13 units

shaalaa.com
Types of Sequencing Problem
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 7: Assignment Problem and Sequencing - Exercise 7.2 [पृष्ठ १२५]

संबंधित प्रश्‍न

A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department

Job I II III
Department A 8 6 5
Department B 8 3 4

Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.


There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.

Jobs I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7

Choose the correct alternative :

The objective of sequencing problem is


If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Choose the correct alternative :

In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:


The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours, while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.


One machine - one job is not an assumption in solving sequencing problems.


State whether the following is True or False :

In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.


State whether the following is True or False :

One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.


State whether the following is True or False :

In a sequencing problem, a machine can process more than one job at a time.


State whether the following is True or False :

The time involved in moving a job from one machine to another is negligibly small.


Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

Solve the following problem :

Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.

Machines Jobs (Processing times in minutes)
I II III IV V VI VII
Machine A 12 6 5 11 5 7 6
Machine B 7 8 9 4 7 8 3

Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.


Solve the following problem :

A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.

Job Shaping (Minutes) Drilling (Minutes) Trapping (Minutes)
1 13 3 18
2 18 8 4
3 8 6 13
4 23 6 8

Choose the correct alternative:

Machine Job
A B C D
I 5 6 8 4
II 4 7 9 10

The optimal sequence for above data is


If there are n jobs and m machines, then there will be _______ sequence of doing jobs.


Choose the correct alternative:

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


In assignment problem each worker or machine is ______ capable of handling any job


______ time is the time when the machine is available but is waiting for a job to be processed


In sequencing problem the time required to transfer a job from one machine to another is ______


State whether the following statement is True or False: 

One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine


State whether the following statement is True or False:

The Total Elapsed is the time required to complete all the jobs i.e. entire task


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False:

In sequencing problem each machine is of different type


A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :

Book I II III IV V
Machine A 4 9 8 6 5
Machine B 5 6 2 3 4
Machine C 8 10 6 7 11

Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.