मराठी
महाराष्ट्र राज्य शिक्षण मंडळएचएससी वाणिज्य (इंग्रजी माध्यम) इयत्ता १२ वी

Solve the following problem : Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Als

Advertisements
Advertisements

प्रश्न

Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6
तक्ता
बेरीज
Advertisements

उत्तर

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

Observe that Min (lathe, grinder) = 1, corresponds to job II on lathe.

∴ Job II is placed first in sequence.

II        

Then the problem reduces to

Job I III IV V
Lathe 4 5 2 5
Surface grinder 3 4 3 6

Now, Min (lathe, grinder) = 2, corresponds to job IV on lathe.

∴ Job IV is placed after II in sequence.

II IV      

Then the problem reduces to

Job I III V
Lathe 4 5 5
Surface grinder 3 4 6

Now, Min (lathe, grinder) = 3, corresponds to job I on grinder.

∴ Job I is placed last in sequence.

II IV     I

Then the problem reduces to

Job III V
Lathe 5 5
Surface grinder 4 6

Now, Min (lathe, grinder) = 4, corresponds to job III on grinder.

∴ Job III is placed before I and V on remaining in sequence.

∴ Optimal sequence is

II IV V III I

Total elapsed time

Job Lath Surface
Grinder
In Out In Out
II (1, 2) 0 1 1 3
IV (2, 3) 1 3 3 6
V (5, 6) 3 8 8 14
III (5, 4) 8 13 14 18
I (4, 3) 13 17 18 21

∴ Total elapsed time = 21 hrs

Idle time for lathe = 21 – 17 = 4 hrs

Idle time for surface grinder = 1 + 2 = 3 hrs.

shaalaa.com
Types of Sequencing Problem
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 7: Assignment Problem and Sequencing - Part II [पृष्ठ १२९]

संबंधित प्रश्‍न

A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.

Job 1 2 3 4 5 6
Time of turning 3 12 5 2 9 11
Time for threading 8 10 9 6 3 1

There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II III IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.

Jobs I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7

Choose the correct alternative :

The objective of sequencing problem is


Choose the correct alternative :

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours, while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.


State whether the following is True or False :

If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.


State whether the following is True or False :

In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.


State whether the following is True or False :

In a sequencing problem, a machine can process more than one job at a time.


State whether the following is True or False :

The time involved in moving a job from one machine to another is negligibly small.


Solve the following problem :

Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.

Machines Jobs (Processing times in minutes)
I II III IV V VI VII
Machine A 12 6 5 11 5 7 6
Machine B 7 8 9 4 7 8 3

Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.


If there are n jobs and m machines, then there will be _______ sequence of doing jobs.


______ time is the time when the machine is available but is waiting for a job to be processed


State whether the following statement is True or False: 

One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False: 

In sequencing problem each job once started on any machine must be processed still its completion


The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______


A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :

Book I II III IV V
Machine A 4 9 8 6 5
Machine B 5 6 2 3 4
Machine C 8 10 6 7 11

Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×