Advertisements
Advertisements
प्रश्न
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Advertisements
उत्तर
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Observe that Min(X, Y) = 2, corresponding to job B on machine X.
∴ Job B is placed first in the sequence.
| B |
Then the problem reduces to
| Job | A | C | D | E |
| Machine X | 10 | 18 | 6 | 20 |
| Machine Y | 4 | 14 | 16 | 8 |
Now, Min(X, Y) = 4, corresponds to job A on machine Y.
∴ Job A is placed last in the sequence.
| B | A |
Then the problem reduces to
| Job | C | D | E |
| Machine X | 18 | 6 | 20 |
| Machine Y | 14 | 16 | 8 |
Now, Min(X, Y) = 6, corresponds to job D on machine X.
∴ Job D is placed second in sequence.
| B | D | A |
Then the problem reduces to
| Job | C | E |
| Machine X | 18 | 20 |
| Machine Y | 14 | 8 |
Now, Min(X, Y) = 8, corresponds to job E on machine Y.
∴ Job E is placed fourth and job C on remaining in sequence.
∴ The optimal sequence is
| B | D | C | E | A |
Total elapsed time,
| Job | Machine X | Machine Y | ||
| In | Out | In | Out | |
| B (2, 12) | 0 | 2 | 2 | 14 |
| D (6, 16) | 2 | 8 | 14 | 30 |
| C (18, 14) | 8 | 26 | 30 | 44 |
| E (20, 8) | 26 | 46 | 46 | 54 |
| A (10, 4) | 46 | 56 | 56 | 60 |
∴ Total elapsed time = 60 hrs.
Idle time for machine X = 60 – 56 = 4 hrs
Idle time for machine Y = 2 + 2 + 2 = 6 hrs.
संबंधित प्रश्न
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
| Job | 1 | 2 | 3 | 4 | 5 | 6 |
| Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
| Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
| Policy | 1 | 2 | 3 |
| Data Entry | 90 | 120 | 180 |
| Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
Choose the correct alternative :
The objective of sequencing problem is
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
| Job | I | II | III | IV | V |
| Lathe | 4 | 1 | 5 | 2 | 5 |
| Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
| Machines | Jobs (Processing times in minutes) | ||||||
| I | II | III | IV | V | VI | VII | |
| Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
| Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
| Type | 1 | 2 | 3 | 4 | 5 |
| Machine A | 16 | 20 | 12 | 14 | 22 |
| Machine B | 10 | 12 | 4 | 6 | 8 |
| Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
In assignment problem each worker or machine is ______ capable of handling any job
______ time is the time when the machine is available but is waiting for a job to be processed
State whether the following statement is True or False:
One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
