English

There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed - Mathematics and Statistics

Advertisements
Advertisements

Question

There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8
Sum
Advertisements

Solution

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Observe that Min(X, Y) = 2, corresponding to job B on machine X.

∴ Job B is placed first in the sequence.

B      

Then the problem reduces to

Job A C D E
Machine X 10 18 6 20
Machine Y 4 14 16 8

Now, Min(X, Y) = 4, corresponds to job A on machine Y.

∴ Job A is placed last in the sequence.

B     A

Then the problem reduces to

Job C D E
Machine X 18 6 20
Machine Y 14 16 8

Now, Min(X, Y) = 6, corresponds to job D on machine X.

∴ Job D is placed second in sequence.

B D     A

Then the problem reduces to

Job C E
Machine X 18 20
Machine Y 14 8

Now, Min(X, Y) = 8, corresponds to job E on machine Y.

∴ Job E is placed fourth and job C on remaining in sequence.

∴ The optimal sequence is

B D C E A

Total elapsed time,

Job Machine X Machine Y
In Out In Out
B (2, 12) 0 2 2 14
D (6, 16) 2 8 14 30
C (18, 14) 8 26 30 44
E (20, 8) 26 46 46 54
A (10, 4) 46 56 56 60

∴ Total elapsed time = 60 hrs.

Idle time for machine X = 60 – 56 = 4 hrs

Idle time for machine Y = 2 + 2 + 2 = 6 hrs.

shaalaa.com
Types of Sequencing Problem
  Is there an error in this question or solution?
Chapter 7: Assignment Problem and Sequencing - Exercise 7.2 [Page 125]

APPEARS IN

Balbharati Mathematics and Statistics 2 (Commerce) [English] Standard 12 Maharashtra State Board
Chapter 7 Assignment Problem and Sequencing
Exercise 7.2 | Q 4 | Page 125

RELATED QUESTIONS

A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department

Job I II III
Department A 8 6 5
Department B 8 3 4

Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.


Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II III IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

Choose the correct alternative :

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


Choose the correct alternative :

In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:


One machine - one job is not an assumption in solving sequencing problems.


State whether the following is True or False :

One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.


State whether the following is True or False :

In a sequencing problem, a machine can process more than one job at a time.


Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

Solve the following problem :

Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.

Machines Jobs (Processing times in minutes)
I II III IV V VI VII
Machine A 12 6 5 11 5 7 6
Machine B 7 8 9 4 7 8 3

Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.


A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Solve the problem for minimizing the total elapsed time.


Choose the correct alternative:

Machine Job
A B C D
I 5 6 8 4
II 4 7 9 10

The optimal sequence for above data is


Choose the correct alternative:

If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______


If there are n jobs and m machines, then there will be _______ sequence of doing jobs.


In assignment problem each worker or machine is ______ capable of handling any job


In sequencing problem the time required to transfer a job from one machine to another is ______


State whether the following statement is True or False: 

One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine


State whether the following statement is True or False:

The Total Elapsed is the time required to complete all the jobs i.e. entire task


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False: 

In sequencing problem each job once started on any machine must be processed still its completion


State whether the following statement is True or False:

In sequencing problem each machine is of different type


Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.

Jobs A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______


A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :

Book I II III IV V
Machine A 4 9 8 6 5
Machine B 5 6 2 3 4
Machine C 8 10 6 7 11

Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×