Advertisements
Advertisements
Question
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
Options
True
False
Advertisements
Solution
True
APPEARS IN
RELATED QUESTIONS
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours, while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
State whether the following is True or False :
The time involved in moving a job from one machine to another is negligibly small.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
| Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
| Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
| Machines | Jobs (Processing times in minutes) | ||||||
| I | II | III | IV | V | VI | VII | |
| Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
| Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
| Type | 1 | 2 | 3 | 4 | 5 |
| Machine A | 16 | 20 | 12 | 14 | 22 |
| Machine B | 10 | 12 | 4 | 6 | 8 |
| Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
| Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
| 1 | 13 | 3 | 18 |
| 2 | 18 | 8 | 4 |
| 3 | 8 | 6 | 13 |
| 4 | 23 | 6 | 8 |
Choose the correct alternative:
If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
In assignment problem each worker or machine is ______ capable of handling any job
______ time is the time when the machine is available but is waiting for a job to be processed
State whether the following statement is True or False:
In sequencing problem each machine is of different type
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
| Book | I | II | III | IV | V |
| Machine A | 4 | 9 | 8 | 6 | 5 |
| Machine B | 5 | 6 | 2 | 3 | 4 |
| Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.
