Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Options
No passing is allowed
Processing times are known
Handling time is negligible
The time of passing depends on the order of machining
Advertisements
Solution
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong The time of passing depends on the order of machining.
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
| Job | 1 | 2 | 3 | 4 | 5 | 6 |
| Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
| Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
| Jobs | I | II | III | IV | V | VI | VII |
| Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
| Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
| Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Choose the correct alternative :
The objective of sequencing problem is
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours, while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.
State whether the following is True or False :
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
| Machines | Jobs (Processing times in minutes) | ||||||
| I | II | III | IV | V | VI | VII | |
| Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
| Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
| Type | 1 | 2 | 3 | 4 | 5 |
| Machine A | 16 | 20 | 12 | 14 | 22 |
| Machine B | 10 | 12 | 4 | 6 | 8 |
| Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
| Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
| 1 | 13 | 3 | 18 |
| 2 | 18 | 8 | 4 |
| 3 | 8 | 6 | 13 |
| 4 | 23 | 6 | 8 |
Choose the correct alternative:
| Machine | Job | |||
| A | B | C | D | |
| I | 5 | 6 | 8 | 4 |
| II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
Choose the correct alternative:
If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
______ time is the time when the machine is available but is waiting for a job to be processed
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type