Advertisements
Advertisements
Question
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Options
No passing is allowed
Processing times are known
Handling time is negligible
The time of passing depends on the order of machining
Advertisements
Solution
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong The time of passing depends on the order of machining.
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
| Job | 1 | 2 | 3 | 4 | 5 | 6 |
| Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
| Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
| Job | I | II | III |
| Department A | 8 | 6 | 5 |
| Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
| Policy | 1 | 2 | 3 |
| Data Entry | 90 | 120 | 180 |
| Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
| Jobs | I | II | III | IV | V | VI | VII |
| Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
| Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
| Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
State whether the following is True or False :
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
| Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
| Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
| Job | I | II | III | IV | V |
| Lathe | 4 | 1 | 5 | 2 | 5 |
| Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
| Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
| 1 | 13 | 3 | 18 |
| 2 | 18 | 8 | 4 |
| 3 | 8 | 6 | 13 |
| 4 | 23 | 6 | 8 |
Choose the correct alternative:
| Machine | Job | |||
| A | B | C | D | |
| I | 5 | 6 | 8 | 4 |
| II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
Choose the correct alternative:
If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
In assignment problem each worker or machine is ______ capable of handling any job
______ time is the time when the machine is available but is waiting for a job to be processed
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
| Jobs | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
| Book | I | II | III | IV | V |
| Machine A | 4 | 9 | 8 | 6 | 5 |
| Machine B | 5 | 6 | 2 | 3 | 4 |
| Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.