English

Solve the following problem : A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these

Advertisements
Advertisements

Question

Solve the following problem :

A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:

Items 1 2 3 4 5 6 7
Time for Cutting 5 7 3 4 6 7 12
Time for Sewing 2 6 7 5 9 5 8

Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.

Sum
Advertisements

Solution

Items 1 2 3 4 5 6 7
Time for Cutting 5 7 3 4 6 7 12
Time for Sewing 2 6 7 5 9 5 8

Observe that Min (cutting, sewing) = 2, corresponds to item 1 on sewing.
∴ Item 1 is placed last in sequence.

            1

Then the problem reduces to

Items 2 3 4 5 6 7
Time for Cutting 7 3 4 6 7 12
Time for Sewing 6 7 5 9 5 8

Now, Min (cutting, sewing) = 3, corresponds to item 3 on cutting.
∴ Item 3 is placed first in sequence.

3           1

Then the problem reduces to

Items 2 4 5 6 7
Time for Cutting 7 4 6 7 12
Time for Sewing 6 5 9 5 8

Now, Min (cutting, sewing) = 4, corresponds to item 4 on cutting.
∴ Item 4 is placed after 3 in sequence.

3 4           1

Item 4 is placed after 3 in sequence.

Items 2 5 6 7
Time for Cutting 7 6 7 12
Time for Sewing 6 9 5 8

Now, Min (cutting, sewing) = 5, corresponds to item 6 on sewing
∴ Item 6 is placed before 1 in sequence.

3 4       6 1

Then the problem reduces to

Items 2 5 7
Time for Cutting 7 6 12
Time for Sewing 6 9 8

Now, Min (cutting, sewing) = 6, corresponds to item 2 on sewing and item 5 on cutting.
∴ Item 2 is placed before 6 and item 5 is placed after 4 and item 7 on remaining in sequence.
∴ Optimal sequence is

3 4 5 7 2 6 1

Total elapsed time

Item Cutting Sewing
In Out In Out
3 (3, 7) 0 3 3 10
4 (4, 5) 3 7 10 15
5 (6, 9) 7 13 15 24
7 (12, 8) 13 25 25 33
2 (7, 6) 25 32 33 39
6 (7, 5) 32 39 39 44
1 (5, 2) 39 44 44 46

∴ Total elapsed time = 46 hrs
Idle time for cutting = 46  44 = 2 hrs
Idle time for sewing = 3 + 1 = 4 hrs.

shaalaa.com
Types of Sequencing Problem
  Is there an error in this question or solution?
Chapter 7: Assignment Problem and Sequencing - Part II [Page 129]

APPEARS IN

Balbharati Mathematics and Statistics 2 (Commerce) [English] Standard 12 Maharashtra State Board
Chapter 7 Assignment Problem and Sequencing
Part II | Q 1 | Page 129

RELATED QUESTIONS

There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II III IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.

Jobs I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7

Choose the correct alternative :

The objective of sequencing problem is


If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Choose the correct alternative :

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


Choose the correct alternative :

In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:


Fill in the blank :

The time for which a machine j does not have a job to process to the start of job is called _______.


The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours, while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.


State whether the following is True or False :

If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.


State whether the following is True or False :

In a sequencing problem, a machine can process more than one job at a time.


State whether the following is True or False :

The time involved in moving a job from one machine to another is negligibly small.


Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

Solve the following problem :

A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.

Job Shaping (Minutes) Drilling (Minutes) Trapping (Minutes)
1 13 3 18
2 18 8 4
3 8 6 13
4 23 6 8

If there are n jobs and m machines, then there will be _______ sequence of doing jobs.


______ time is the time when the machine is available but is waiting for a job to be processed


State whether the following statement is True or False: 

One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False: 

In sequencing problem each job once started on any machine must be processed still its completion


State whether the following statement is True or False:

In sequencing problem each machine is of different type


The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×