Advertisements
Advertisements
Question
State whether the following is True or False :
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.
Options
True
False
Advertisements
Solution
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine True.
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
| Job | 1 | 2 | 3 | 4 | 5 | 6 |
| Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
| Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
| Job | I | II | III |
| Department A | 8 | 6 | 5 |
| Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
| Policy | 1 | 2 | 3 |
| Data Entry | 90 | 120 | 180 |
| Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
| Job | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
| Jobs | I | II | III | IV | V | VI | VII |
| Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
| Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
| Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Choose the correct alternative :
The objective of sequencing problem is
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is ______.
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
State whether the following is True or False :
The time involved in moving a job from one machine to another is negligibly small.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
| Job | I | II | III | IV | V |
| Lathe | 4 | 1 | 5 | 2 | 5 |
| Surface grinder | 3 | 2 | 4 | 3 | 6 |
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
State whether the following statement is True or False:
One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each machine is of different type
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
| Jobs | A | B | C | D | E |
| Machine X | 10 | 2 | 18 | 6 | 20 |
| Machine Y | 4 | 12 | 14 | 16 | 8 |
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______
