English

Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hrs.

Advertisements
Advertisements

Questions

Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.

Jobs I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7

Find the appropriate regression equation and use it to estimate the blood pressure of a woman with age 47 years. Find the optimal sequence that minimizes total time required to complete the following jobs in order A-B-C. The processing times are given in hrs.

Job I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7
Chart
Sum
Advertisements

Solution

Job I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7

Here min A = 5, max B = 5, min C = 3

Since min A ≥ max B is satisfied, the problem can be converted into a two machine problem.

Let G and H be two fictitious machines such that G = A + B and H = B + C

Then the problem can be written as

Job I II III IV V VI VII
Machine G 10 10 7 16 7 12 15
Machine H 7 11 9 9 10 13 10

Observe that Min (G, H) = 7, corresponds to job I on machine H, job III on machine G and job V on machine G.

∴ Job I is placed last in sequence, Job III and V are placed either first or second in sequence.

V III         I
OR
III V         I

Then the problem reduces to

Job II IV VI VII
Machine G 10 16 12 15
Machine H 11 9 13 10

Now, Min (G, H) = 9, corresponds to Job IV on machine H.

∴ Job IV is placed second last in the sequence.

V III       IV I
OR
III V       IV I

Then the problem reduces to

Job II VI VII
Machine G 10 12 15
Machine H 11 13 10

Now, Min (G, H) = 10, corresponds to Job II on machine G and Job VII on machine H.

∴  Job II is placed third in the sequence, Job VII is placed third last in the sequence and remaining Job VI is placed fourth in the sequence.

V III II VI VII IV I
OR
III V II VI VII IV I

∴ We consider the optimal sequence as V – III – II – VI – VII – IV – I

Total elapsed time

Job Machine
A
Machine
B
Machine
C
In Out In  Out In  Out
V (6, 1, 9) 0 6 6 7 7 16
III (5, 2, 7) 6 11 11 13 16 23
II (7, 3, 8) 11 18 18 21 23 31
VI (7, 5, 8) 18 25 25 30 31 39
VII (12, 3, 7) 25 37 37 40 40 47
IV (11, 5, 4) 37 48 48 53 53 57
I (6, 4, 3) 48 54 54 58 58 61

Total elapsed time = 61 hrs

Idle time for Machine A = 61 –  54 = 7 hrs

Idle time for Machine B = (61 – 58) + 6 + 4 + 5 + 4 + 7 + 8 + 1 = 38 hrs

Idle time for Machine C = 7 + 1 + 6 + 1 = 15 hrs.

shaalaa.com
Types of Sequencing Problem
  Is there an error in this question or solution?
Chapter 7: Assignment Problem and Sequencing - Exercise 7.2 [Page 125]

RELATED QUESTIONS

Choose the correct alternative :

The objective of sequencing problem is


If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Choose the correct alternative :

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


Fill in the blank :

The time for which a machine j does not have a job to process to the start of job is called _______.


One machine - one job is not an assumption in solving sequencing problems.


State whether the following is True or False :

If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.


State whether the following is True or False :

One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.


State whether the following is True or False :

In a sequencing problem, a machine can process more than one job at a time.


Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

Solve the following problem :

Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.

Machines Jobs (Processing times in minutes)
I II III IV V VI VII
Machine A 12 6 5 11 5 7 6
Machine B 7 8 9 4 7 8 3

Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.


A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Solve the problem for minimizing the total elapsed time.


Solve the following problem :

A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.

Job Shaping (Minutes) Drilling (Minutes) Trapping (Minutes)
1 13 3 18
2 18 8 4
3 8 6 13
4 23 6 8

Choose the correct alternative:

Machine Job
A B C D
I 5 6 8 4
II 4 7 9 10

The optimal sequence for above data is


Choose the correct alternative:

If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______


If there are n jobs and m machines, then there will be _______ sequence of doing jobs.


Choose the correct alternative:

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


In assignment problem each worker or machine is ______ capable of handling any job


______ time is the time when the machine is available but is waiting for a job to be processed


State whether the following statement is True or False:

The Total Elapsed is the time required to complete all the jobs i.e. entire task


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False:

In sequencing problem each machine is of different type


Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.

Jobs A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×