Advertisements
Advertisements
Question
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
Advertisements
Solution
P can do a piece of work in 12 days.
∴ P’s 1 day work = `1/12`
P’s 3 day’s work = `3 xx 1/12 = 3/12`
Q can do a piece of work in 15 days.
∴ Q’s 1 day work = `1/15`
Remaining work after 3 days = `1 - 3/12 = 9/12`
(P + Q)'s 1 day work = `1/2 + 1/15`
= `5/60 + 4/60`
= `9/60`
∴ Number of days required to finish the remaining work 9
= `"Remaining work"/(("P" + "Q")"'s" 1 "day work")`
= `(9/12)/(9/60)`
= `9/12 xx 60/9`
= 5
Remaining work lasts for 5 days
Total work lasts for 3 + 5 = 8 days.
APPEARS IN
RELATED QUESTIONS
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?
