Advertisements
Advertisements
Question
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
Advertisements
Solution
P can do a piece of work in 12 days.
∴ P’s 1 day work = `1/12`
P’s 3 day’s work = `3 xx 1/12 = 3/12`
Q can do a piece of work in 15 days.
∴ Q’s 1 day work = `1/15`
Remaining work after 3 days = `1 - 3/12 = 9/12`
(P + Q)'s 1 day work = `1/2 + 1/15`
= `5/60 + 4/60`
= `9/60`
∴ Number of days required to finish the remaining work 9
= `"Remaining work"/(("P" + "Q")"'s" 1 "day work")`
= `(9/12)/(9/60)`
= `9/12 xx 60/9`
= 5
Remaining work lasts for 5 days
Total work lasts for 3 + 5 = 8 days.
APPEARS IN
RELATED QUESTIONS
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
