Question

In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?

Sum
Advertisements

Solution

Let x be number of men required 60 men can do the work in = 28 days

1 man can do the work in = 28 x 60 days
x man can do the work in = `(28xx60)/"x"` day

But `(28xx60)/"x"` = 40 days  ......(Given)

∴ x =`(28xx60)/40` =7 × 6 = 42

Required number of men = 42

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (C) [Page 125]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (C) | Q 3 | Page 125

RELATED QUESTIONS

A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×