Question
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
Advertisements
Solution
Let x be number of men required 60 men can do the work in = 28 days
1 man can do the work in = 28 x 60 days
x man can do the work in = `(28xx60)/"x"` day
But `(28xx60)/"x"` = 40 days ......(Given)
∴ x =`(28xx60)/40` =7 × 6 = 42
Required number of men = 42
APPEARS IN
RELATED QUESTIONS
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?