Question

In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?

Sum
Advertisements

Solution

Let x be number of men required 60 men can do the work in = 28 days

1 man can do the work in = 28 x 60 days
x man can do the work in = `(28xx60)/"x"` day

But `(28xx60)/"x"` = 40 days  ......(Given)

∴ x =`(28xx60)/40` =7 × 6 = 42

Required number of men = 42

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (C) [Page 125]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (C) | Q 3 | Page 125

RELATED QUESTIONS

12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×