Question

A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?

Sum
Advertisements

Solution

A's one day's work =`1/10`

B's one day's work =`1/12`

C's one day's work =`1/15`

A, B and C's one day's work =`1/10+1/12+1/15`

`=(6+5+4)/60=15/60=1/4`

Let the work completed in x days

∴ A's 2 days work + B's (x − 3) days work + C's x days work = 1

`⇒2xx1/10+("x"-3)xx1/12+"x"xx1/15=1`

`⇒1/5+("x"-3)/12+"x"/15=1`

`(12+5"x"-15+4"x"=60)/60` ...(L.C.M of 5, 12, 15 = 60)

⇒ 9x = 60 − 12 + 15

⇒ 9x = 63

`⇒"x"=63/9=7`

∴ Work will last for 7 days

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (E) [Page 133]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (E) | Q 15 | Page 133

RELATED QUESTIONS

22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?


A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×