Question

72 men do a piece of work in 25 days. In how many days will 30 men do the same work?

Sum
Advertisements

Solution

Men: Days:: Men : Days

  72 :   25  ::   30  :    x

∴ By inverse proportion

72 × 25 = 30 × x

`⇒"x"=(25xx72)/30`

= 60 days

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (B) [Page 123]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (B) | Q 6 | Page 123

RELATED QUESTIONS

A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×