72 men do a piece of work in 25 days. In how many days will 30 men do the same work?

Sum
Advertisements

Solution

Men: Days:: Men : Days

  72 :   25  ::   30  :    x

∴ By inverse proportion

72 × 25 = 30 × x

`⇒"x"=(25xx72)/30`

= 60 days

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (B) [Page 123]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (B) | Q 6 | Page 123

RELATED QUESTIONS

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?


12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×