Question
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?
Advertisements
Solution
`1/2` of the work is done by P in 6 days
∴ Full work is done by P in `6/(1/2)` = 6 × 2 = 12 days
`2/3` of work done by Q in 4 days.
∴ Full work is done by Q in `4/(2/3) = 4 xx 3/2` = 6 days
(P + Q) will finish the whole work in `"ab"/("a" + "b")` days
= `(12 xx 6)/(12 + 6)`
= `(12 xx 6)/18`
= 4 days
(P + Q) will finish `(-3)/4` of the work in `4 xx 3/4` = 3 days.
APPEARS IN
RELATED QUESTIONS
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.