P alone can do 12 of a work in 6 days and Q alone can do 23 of the same work in 4 days. in how many days will they finish 34 of the work, working together?

Advertisements
Advertisements

प्रश्न

P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?

योग
Advertisements

उत्तर

`1/2` of the work is done by P in 6 days

∴ Full work is done by P in `6/(1/2)` = 6 × 2 = 12 days

`2/3` of work done by Q in 4 days.

∴ Full work is done by Q in `4/(2/3) = 4 xx 3/2` = 6 days

(P + Q) will finish the whole work in `"ab"/("a" + "b")` days

= `(12 xx 6)/(12 + 6)`

= `(12 xx 6)/18`

= 4 days

(P + Q) will finish `(-3)/4` of the work in `4 xx 3/4` = 3 days.

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 4: Life Mathematics - Exercise 4.5 [पृष्ठ १५२]

APPEARS IN

सामाचीर कलवी Mathematics [English] Class 8 TN Board
अध्याय 4 Life Mathematics
Exercise 4.5 | Q 14 | पृष्ठ १५२

संबंधित प्रश्न

If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×