Advertisements
Advertisements
प्रश्न
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
Advertisements
उत्तर
12 men = 18 women
∴ 4 m =`18/12xx4`
= 6 women
Total women in second case = 4 men + 8 women
6 + 8 = 14 women
18 women can do a piece of work in 7 days
Let 14 women will do the same work in x days
∴ 18: 14: : 7: x ........(Less women, more days)
⇒ 18 : 14 : : x : 7
x = `(18xx7)/14` .......(Using inverse proportion)
= 9
∴ They will complete the work in 9 days
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?