If 12 Men Or 18 Women Can Complete a Piece of Work in 7 Days, in How Many Days Can 4 Men and 8 Women Complete the Same Work?

Advertisements
Advertisements

प्रश्न

If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?

योग
Advertisements

उत्तर

12 men = 18 women

∴ 4 m =`18/12xx4`

= 6 women

Total women in second case = 4 men + 8 women

6 + 8 = 14 women

18 women can do a piece of work in 7 days

Let 14 women will do the same work in x days

∴ 18: 14: : 7: x ........(Less women, more days)

⇒ 18 : 14 : : x : 7 

x = `(18xx7)/14` .......(Using inverse proportion)

= 9 

∴ They will complete the work in 9 days

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (C) [पृष्ठ १२६]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (C) | Q 11 | पृष्ठ १२६

संबंधित प्रश्न

72 men do a piece of work in 25 days. In how many days will 30 men do the same work?


Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×