प्रश्न
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
Advertisements
उत्तर
3 men = 6 boys
4 men = `6/3xx4` = 8
Total boys in second case :
= 4 men + 12 boys = 8 + 12 = 20 boys
6 boys can do a piece of work in 20 days
Then let 20 boys will do the same work in x days
∴ 6 : 20 : : 20 : x ........(More boys,less days)
⇒ 6 : 20 : : x : 20 ....(By inverse proportion)
x = `(20xx6)/20`
= 6 days
∴ They will do the work in 6 days
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?