Advertisements
Advertisements
प्रश्न
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
Advertisements
उत्तर
A and B complete a piece of work in = 24 days
B and C complete a piece of work in = 36 days
(A+B+C) complete a piece of work in = 18 days
(A+B)’s 1-day work = `1/24`
(B+C)’s 1-day work = `1/36`
(A+B+C)’s 1-day work = `1/18`
(i) A's 1-day work =`1/18-1/36`
`=(2-1)/36=1/36`
∴ A will complete the work in = 36 days
(ii) C's 1-day work =`1/18-1/24`
`=(4-3)/72=1/72`
∴ C will complete the work in = 72 days
(iii) (A+C)'s 1-day work =`1/36+1/72`
`=(2+1)/72=3/72`
`=1/24`
∴ (A+C) will complete the work in = 24 days
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?
