प्रश्न
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
Advertisements
उत्तर
A can-do `1/4` of work in = 5 days
A can-do 1 work in = 5 × 4 days
= 20 days
B can do `1/3` of work in = 10 days
B can do 1 work in = 10 × 3 days
= 30 days
A's 1-day work =`1/20`
B's 1-day work =`1/30`
(A+B)'s 1 day work =`1/20+1/30`
`=(3+2)/60`
`=5/60`
`=1/12`
∴ A and B working together will complete the work in = 12 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?