प्रश्न
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
Advertisements
उत्तर
A's 1-day work = `1/15`
B's 1-day work = `1/20`
(A+B)'s 1-day work =`1/15+1/20`
`=(4+3)/60=7/60`
(A+B)'s 4 days work =`7/60xx4=7/15`
Remaining work =`1-7/15=(15-7)/15`
`=8/15`
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?