A Can Do a Work in 15 Days and B in 20 Days. If They Together Work on It for 4 Days; What Fraction of the Work Will Be Left?

Advertisements
Advertisements

प्रश्न

A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?

योग
Advertisements

उत्तर

A's 1-day work = `1/15`

B's 1-day work = `1/20`

(A+B)'s 1-day work =`1/15+1/20`

`=(4+3)/60=7/60`

(A+B)'s 4 days work =`7/60xx4=7/15`

Remaining work =`1-7/15=(15-7)/15`

`=8/15`

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (E) | Q 3 | पृष्ठ १३३

संबंधित प्रश्न

A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?


A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?