प्रश्न
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
Advertisements
उत्तर
A's 1-day work = `1/15`
B's 1-day work = `1/20`
(A+B)'s 1-day work =`1/15+1/20`
`=(4+3)/60=7/60`
(A+B)'s 4 days work =`7/60xx4=7/15`
Remaining work =`1-7/15=(15-7)/15`
`=8/15`
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?