प्रश्न
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
Advertisements
उत्तर
Let x be number of men required 60 men can do the work in = 28 days
1 man can do the work in = 28 x 60 days
x man can do the work in = `(28xx60)/"x"` day
But `(28xx60)/"x"` = 40 days ......(Given)
∴ x =`(28xx60)/40` =7 × 6 = 42
Required number of men = 42
APPEARS IN
संबंधित प्रश्न
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.