प्रश्न
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
Advertisements
उत्तर
Let x be number of men required 60 men can do the work in = 28 days
1 man can do the work in = 28 x 60 days
x man can do the work in = `(28xx60)/"x"` day
But `(28xx60)/"x"` = 40 days ......(Given)
∴ x =`(28xx60)/40` =7 × 6 = 42
Required number of men = 42
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?