A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
Advertisements
उत्तर
A and B can do a work in = 8 days
B and C can do a work in = 12 days
A and C can do a work in = 16 days
(A+B)’s 1-day work =`1/8`
(B+C)’s 1-day work =`1/12`
(A+C)'s 1-day work =`1/16`
∴ [(A+B)+(B+C)+(A+C)]'s 1 day work
`=1/8+1/12+1/16`
i.e. [A+B+B+C+A+C]'s 1 day work
`=1/8+1/12+1/16`
`=(6+4+3)/48=13/48`
i.e. 2(A+B+C)'s 1-day work =`13/48`
i.e. (A+B+C)'s 1-day work =`13/48xx1/2=13/96`
∴ (A+B+C) can do the work in =`96/13`days
`=7 5/13` days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?