If 56 Workers Can Build a Wall in 180 Hours, How Many Workers Will Be Required to Do the Same Work in 70 Hours? - Mathematics

Advertisements
Advertisements

प्रश्न

If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?

बेरीज
Advertisements

उत्तर

Workers: Hours:: Workers: Hours

   56     :    180  ::     x       :   70

∴ By inverse proportion

56 × 180 = x × 70

`⇒"x"=(180xx56)/70`

= 144 workers

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (B) [पृष्ठ १२३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (B) | Q 7 | पृष्ठ १२३

संबंधित प्रश्‍न

12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?