A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
Advertisements
उत्तर
A's 1-day work =`1/10`
B's 1-day work =`1/15`
(A + B)'s 1-day work =`1/10+1/15`
`=(3+2)/30=5/30`
`=1/6`
∴ Both A and B together can finish the work in = 6 days
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?