प्रश्न
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
Advertisements
उत्तर
Strength of garrison = 480 men
Strength reduced by = 160 men
New strength of garrison = 480 − 160 = 320
Provision for 480 men lasts for = 12 days
Provision for 1 man last for = 480 × 12 days
Provision for 320 men lasts for =`(480xx12)/320` days
`=(3xx12)/2` = 18 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?