प्रश्न
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
Advertisements
उत्तर
A can do a piece of work in = 24 days
(A+B) can do a piece of work in = 16 days
(A+B+C) can do a piece of work in
`=10 2/3`days = `32/3` days
∴ A's 1-day work =`1/24`
(A+B)'s 1 day work =`1/16`
(A+B+C)'s 1 day work =`3/32`
C's 1 day work =`3/32-1/16`
`=(3-2)/32=1/32`
(A+C)'s 1-day work =`1/24+1/32`
`=(4+3)/96=7/96`
∴ (A+C) can do the work in =`96/7` days
`=13 5/7` days
APPEARS IN
संबंधित प्रश्न
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?