A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
Advertisements
उत्तर
A and B can do a piece of work in = 40 days
B and C can do a piece of work in = 30 days
C and A can do a piece of work in = 24 days
(A+B)’s 1-day work =`1/40`
(B+C)’s 1-day work =`1/30`
(C+A)’s 1-day work =`1/24`
(i) [(A+B)+(B+C)+(C+A)]’s 1 day work = `1/40+1/30+1/24`
`=(3+4+5)/120`
`=12/120=1/10`
i.e. (A+B+B+C+C+A)'s 1-day work =`1/10`
i.e. 2 (A+B+C)'s 1-day work =`1/10`
∴ (A+B+C)'s 1-day work =`1/10xx1/2`
`=1/20`
∴ (A+B+C) can do the work in = 20 days
(ii) A's 1-day work =`1/20-1/30`
`=(3-2)/60=1/60`
∴ A can do the work in 60 days
B's 1-day work =`1/20-1/24`
`=(6-5)/120=1/120`
∴ B can do the work in 120 days
now, C's 1-day work =`1/20-1/40`
`=(2-1)/40=1/40`
C can do the work in 40 days
Hence A can do the work in = 60 days
B can do the work in = 120 days
C can do the work in = 40 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.