A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?

बेरीज
Advertisements

उत्तर

A's 1-day work = `1/15`

B's 1-day work = `1/20`

(A+B)'s 1-day work =`1/15+1/20`

`=(4+3)/60=7/60`

(A+B)'s 4 days work =`7/60xx4=7/15`

Remaining work =`1-7/15=(15-7)/15`

`=8/15`

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (E) | Q 3 | पृष्ठ १३३

संबंधित प्रश्‍न

22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?


A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×