A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
Advertisements
उत्तर
A's 1-day work = `1/15`
B's 1-day work = `1/20`
(A+B)'s 1-day work =`1/15+1/20`
`=(4+3)/60=7/60`
(A+B)'s 4 days work =`7/60xx4=7/15`
Remaining work =`1-7/15=(15-7)/15`
`=8/15`
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?