प्रश्न
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
Advertisements
उत्तर
3 men = 6 boys
4 men = `6/3xx4` = 8
Total boys in second case :
= 4 men + 12 boys = 8 + 12 = 20 boys
6 boys can do a piece of work in 20 days
Then let 20 boys will do the same work in x days
∴ 6 : 20 : : 20 : x ........(More boys,less days)
⇒ 6 : 20 : : x : 20 ....(By inverse proportion)
x = `(20xx6)/20`
= 6 days
∴ They will do the work in 6 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?