If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?

बेरीज
Advertisements

उत्तर

3 men = 6 boys

4 men = `6/3xx4` = 8

Total boys in second case :
= 4 men + 12 boys = 8 + 12 = 20 boys

6 boys can do a piece of work in 20 days

Then let 20 boys will do the same work in x days

∴ 6 : 20 : : 20 : x ........(More boys,less days)

⇒ 6 : 20 : : x : 20 ....(By inverse proportion)

x = `(20xx6)/20` 

= 6 days

∴ They will do the work in 6 days

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (C) [पृष्ठ १२६]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (C) | Q 12 | पृष्ठ १२६

संबंधित प्रश्‍न

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?


If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×