90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Advertisements
उत्तर
In 24 days, working 8 hours a day, work can be completed by = 90 men
In 1 day, working 8 hours a day, work can be completed by = 90 × 24 men
In 18 days, working 8 hours a day, work can be completed by =`(90xx24)/18` men
In 18 days, working 1 hour a day, work can be completed by = `(90xx24)/18xx8` men
In 18 days, working `7 1/2` i.e. `15/2` hours a day, work can be completed by =`(90xx24xx8)/18xx2/15` men
`=(90xx24xx8xx2)/(18xx15)=(1xx24xx8xx2)/3` = 128 men
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?