90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Advertisements
उत्तर
In 24 days, working 8 hours a day, work can be completed by = 90 men
In 1 day, working 8 hours a day, work can be completed by = 90 × 24 men
In 18 days, working 8 hours a day, work can be completed by =`(90xx24)/18` men
In 18 days, working 1 hour a day, work can be completed by = `(90xx24)/18xx8` men
In 18 days, working `7 1/2` i.e. `15/2` hours a day, work can be completed by =`(90xx24xx8)/18xx2/15` men
`=(90xx24xx8xx2)/(18xx15)=(1xx24xx8xx2)/3` = 128 men
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?