प्रश्न
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
Advertisements
उत्तर
Given,
A can do a piece of work in = 20 days
B can do a piece of work in = 15 days
∴ A's 1-day work =`1/20`
B's 1-day work = `1/15`
(A+B)'s 1-day work =`1/20+1/15`
`=(3+4)/60=7/60`
(A+B)'s 6 days work =`7/60xx6=7/10`
Remaining work =`1-7/10`
`=(10-7)/10=3/10`
B can do 1 work in = 15 days
B can do `3/10` work in =`15xx3/10` days
`=45/10`days =`9/2` days = `4 1/2` days
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?