प्रश्न
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
Advertisements
उत्तर
Given,
A can do a piece of work in = 20 days
B can do a piece of work in = 15 days
∴ A's 1-day work =`1/20`
B's 1-day work = `1/15`
(A+B)'s 1-day work =`1/20+1/15`
`=(3+4)/60=7/60`
(A+B)'s 6 days work =`7/60xx6=7/10`
Remaining work =`1-7/10`
`=(10-7)/10=3/10`
B can do 1 work in = 15 days
B can do `3/10` work in =`15xx3/10` days
`=45/10`days =`9/2` days = `4 1/2` days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?