Question
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
Advertisements
Solution
Given,
A can do a piece of work in = 20 days
B can do a piece of work in = 15 days
∴ A's 1-day work =`1/20`
B's 1-day work = `1/15`
(A+B)'s 1-day work =`1/20+1/15`
`=(3+4)/60=7/60`
(A+B)'s 6 days work =`7/60xx6=7/10`
Remaining work =`1-7/10`
`=(10-7)/10=3/10`
B can do 1 work in = 15 days
B can do `3/10` work in =`15xx3/10` days
`=45/10`days =`9/2` days = `4 1/2` days
APPEARS IN
RELATED QUESTIONS
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?