A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?

Sum
Advertisements

Solution

Given,

A can do a piece of work in = 20 days

B can do a piece of work in = 15 days

∴ A's 1-day work =`1/20`

B's 1-day work = `1/15`

(A+B)'s 1-day work =`1/20+1/15`

`=(3+4)/60=7/60`

(A+B)'s 6 days work =`7/60xx6=7/10`

Remaining work =`1-7/10`

`=(10-7)/10=3/10`

B can do 1 work in = 15 days

B can do `3/10` work in =`15xx3/10` days

`=45/10`days =`9/2` days = `4 1/2` days

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (E) [Page 133]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (E) | Q 7 | Page 133

RELATED QUESTIONS

22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?


A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


72 men do a piece of work in 25 days. In how many days will 30 men do the same work?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×