Question
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
Advertisements
Solution
Strength of garrison = 480 men
Strength reduced by = 160 men
New strength of garrison = 480 − 160 = 320
Provision for 480 men lasts for = 12 days
Provision for 1 man last for = 480 × 12 days
Provision for 320 men lasts for =`(480xx12)/320` days
`=(3xx12)/2` = 18 days
APPEARS IN
RELATED QUESTIONS
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?