Question
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
Advertisements
Solution
12 men = 18 women
∴ 4 m =`18/12xx4`
= 6 women
Total women in second case = 4 men + 8 women
6 + 8 = 14 women
18 women can do a piece of work in 7 days
Let 14 women will do the same work in x days
∴ 18: 14: : 7: x ........(Less women, more days)
⇒ 18 : 14 : : x : 7
x = `(18xx7)/14` .......(Using inverse proportion)
= 9
∴ They will complete the work in 9 days
APPEARS IN
RELATED QUESTIONS
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?