If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
Advertisements
उत्तर
12 men = 18 women
∴ 4 m =`18/12xx4`
= 6 women
Total women in second case = 4 men + 8 women
6 + 8 = 14 women
18 women can do a piece of work in 7 days
Let 14 women will do the same work in x days
∴ 18: 14: : 7: x ........(Less women, more days)
⇒ 18 : 14 : : x : 7
x = `(18xx7)/14` .......(Using inverse proportion)
= 9
∴ They will complete the work in 9 days
APPEARS IN
संबंधित प्रश्न
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?