If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
Advertisements
उत्तर
12 men = 18 women
∴ 4 m =`18/12xx4`
= 6 women
Total women in second case = 4 men + 8 women
6 + 8 = 14 women
18 women can do a piece of work in 7 days
Let 14 women will do the same work in x days
∴ 18: 14: : 7: x ........(Less women, more days)
⇒ 18 : 14 : : x : 7
x = `(18xx7)/14` .......(Using inverse proportion)
= 9
∴ They will complete the work in 9 days
APPEARS IN
संबंधित प्रश्न
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?