If 12 Men Or 18 Women Can Complete a Piece of Work in 7 Days, in How Many Days Can 4 Men and 8 Women Complete the Same Work?

Advertisements
Advertisements

प्रश्न

If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?

बेरीज
Advertisements

उत्तर

12 men = 18 women

∴ 4 m =`18/12xx4`

= 6 women

Total women in second case = 4 men + 8 women

6 + 8 = 14 women

18 women can do a piece of work in 7 days

Let 14 women will do the same work in x days

∴ 18: 14: : 7: x ........(Less women, more days)

⇒ 18 : 14 : : x : 7 

x = `(18xx7)/14` .......(Using inverse proportion)

= 9 

∴ They will complete the work in 9 days

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (C) [पृष्ठ १२६]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (C) | Q 11 | पृष्ठ १२६

संबंधित प्रश्‍न

12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×