36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
Advertisements
उत्तर
Men: Days:: Men: Days
36 : 7 :: x : 42
∴ By inverse proportional
36 × 7 = x × 42
`⇒"x"=(36xx7)/42`
= 6 men
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?