प्रश्न

12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?

बेरीज
Advertisements

उत्तर

Pipes: Time:: Pipes: Time

  12  :    2x  ::   21  :  42

∴ By inverse proportion

12 × 42 = 21 × x

`⇒"x"=(12xx42)/21`

= 24 minutes

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (B) [पृष्ठ १२३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (B) | Q 4 | पृष्ठ १२३

संबंधित प्रश्‍न

A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?


A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×