P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
Advertisements
उत्तर
P can do a piece of work in 12 days.
∴ P’s 1 day work = `1/12`
P’s 3 day’s work = `3 xx 1/12 = 3/12`
Q can do a piece of work in 15 days.
∴ Q’s 1 day work = `1/15`
Remaining work after 3 days = `1 - 3/12 = 9/12`
(P + Q)'s 1 day work = `1/2 + 1/15`
= `5/60 + 4/60`
= `9/60`
∴ Number of days required to finish the remaining work 9
= `"Remaining work"/(("P" + "Q")"'s" 1 "day work")`
= `(9/12)/(9/60)`
= `9/12 xx 60/9`
= 5
Remaining work lasts for 5 days
Total work lasts for 3 + 5 = 8 days.
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?