प्रश्न
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
Advertisements
उत्तर
P can do a piece of work in 12 days.
∴ P’s 1 day work = `1/12`
P’s 3 day’s work = `3 xx 1/12 = 3/12`
Q can do a piece of work in 15 days.
∴ Q’s 1 day work = `1/15`
Remaining work after 3 days = `1 - 3/12 = 9/12`
(P + Q)'s 1 day work = `1/2 + 1/15`
= `5/60 + 4/60`
= `9/60`
∴ Number of days required to finish the remaining work 9
= `"Remaining work"/(("P" + "Q")"'s" 1 "day work")`
= `(9/12)/(9/60)`
= `9/12 xx 60/9`
= 5
Remaining work lasts for 5 days
Total work lasts for 3 + 5 = 8 days.
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?