A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
Advertisements
उत्तर
A can do a piece of work in = 10 days
B can do a piece of work in = 18 days
(A+B+C) can do a piece of work in = 4 days
∴ A's 1-day work =`1/10`
B's 1-day work = `1/18`
(A+B)'s 1-day work =`1/10+1/18=(9+5)/90`
`=14/90=7/45`
(A+B+C)'s 1-day work =`1/4`
∴ C's 1-day work =`1/4-7/45`
`=(45-28)/180=17/180`
∴ C can do the piece of work in = `180/17` days
`=10 10/17` days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?