A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?

योग
Advertisements

उत्तर

A can do a piece of work in = 10 days

B can do a piece of work in = 18 days

(A+B+C) can do a piece of work in = 4 days

∴ A's 1-day work =`1/10`

B's 1-day work = `1/18`

(A+B)'s 1-day work =`1/10+1/18=(9+5)/90`

`=14/90=7/45`

(A+B+C)'s 1-day work =`1/4`

∴ C's 1-day work =`1/4-7/45`

`=(45-28)/180=17/180`

∴ C can do the piece of work in = `180/17` days

`=10 10/17` days

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (E) | Q 9 | पृष्ठ १३३

संबंधित प्रश्न

22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?


In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?


72 men do a piece of work in 25 days. In how many days will 30 men do the same work?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×