प्रश्न
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
Advertisements
उत्तर
A can do a piece of work in = 10 days
B can do a piece of work in = 18 days
(A+B+C) can do a piece of work in = 4 days
∴ A's 1-day work =`1/10`
B's 1-day work = `1/18`
(A+B)'s 1-day work =`1/10+1/18=(9+5)/90`
`=14/90=7/45`
(A+B+C)'s 1-day work =`1/4`
∴ C's 1-day work =`1/4-7/45`
`=(45-28)/180=17/180`
∴ C can do the piece of work in = `180/17` days
`=10 10/17` days
APPEARS IN
संबंधित प्रश्न
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?