प्रश्न
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
Advertisements
उत्तर
A and B can do a piece of work in = 40 days
B and C can do a piece of work in = 30 days
C and A can do a piece of work in = 24 days
(A+B)’s 1-day work =`1/40`
(B+C)’s 1-day work =`1/30`
(C+A)’s 1-day work =`1/24`
(i) [(A+B)+(B+C)+(C+A)]’s 1 day work = `1/40+1/30+1/24`
`=(3+4+5)/120`
`=12/120=1/10`
i.e. (A+B+B+C+C+A)'s 1-day work =`1/10`
i.e. 2 (A+B+C)'s 1-day work =`1/10`
∴ (A+B+C)'s 1-day work =`1/10xx1/2`
`=1/20`
∴ (A+B+C) can do the work in = 20 days
(ii) A's 1-day work =`1/20-1/30`
`=(3-2)/60=1/60`
∴ A can do the work in 60 days
B's 1-day work =`1/20-1/24`
`=(6-5)/120=1/120`
∴ B can do the work in 120 days
now, C's 1-day work =`1/20-1/40`
`=(2-1)/40=1/40`
C can do the work in 40 days
Hence A can do the work in = 60 days
B can do the work in = 120 days
C can do the work in = 40 days
APPEARS IN
संबंधित प्रश्न
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?