प्रश्न
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
Advertisements
उत्तर
A and B can do a piece of work in = 40 days
B and C can do a piece of work in = 30 days
C and A can do a piece of work in = 24 days
(A+B)’s 1-day work =`1/40`
(B+C)’s 1-day work =`1/30`
(C+A)’s 1-day work =`1/24`
(i) [(A+B)+(B+C)+(C+A)]’s 1 day work = `1/40+1/30+1/24`
`=(3+4+5)/120`
`=12/120=1/10`
i.e. (A+B+B+C+C+A)'s 1-day work =`1/10`
i.e. 2 (A+B+C)'s 1-day work =`1/10`
∴ (A+B+C)'s 1-day work =`1/10xx1/2`
`=1/20`
∴ (A+B+C) can do the work in = 20 days
(ii) A's 1-day work =`1/20-1/30`
`=(3-2)/60=1/60`
∴ A can do the work in 60 days
B's 1-day work =`1/20-1/24`
`=(6-5)/120=1/120`
∴ B can do the work in 120 days
now, C's 1-day work =`1/20-1/40`
`=(2-1)/40=1/40`
C can do the work in 40 days
Hence A can do the work in = 60 days
B can do the work in = 120 days
C can do the work in = 40 days
APPEARS IN
संबंधित प्रश्न
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?