90 Men Can Complete a Work in 24 Days Working 8 Hours a Day. How Many Men Are Required to Complete the Same Work in 18 Days Working 7 1/2 Hours a Day?

Advertisements
Advertisements

प्रश्न

90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?

योग
Advertisements

उत्तर

In 24 days, working 8 hours a day, work can be completed by = 90 men

In 1 day, working 8 hours a day, work can be completed by = 90 × 24 men

In 18 days, working 8 hours a day, work can be completed by =`(90xx24)/18` men

In 18 days, working 1 hour a day, work can be completed by = `(90xx24)/18xx8` men

In 18 days, working `7 1/2` i.e. `15/2` hours a day, work can be completed by =`(90xx24xx8)/18xx2/15` men

`=(90xx24xx8xx2)/(18xx15)=(1xx24xx8xx2)/3` = 128 men

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (D) [पृष्ठ १२९]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (D) | Q 7 | पृष्ठ १२९

संबंधित प्रश्न

A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.