X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?
Advertisements
उत्तर
X can do the work in 6 days.
X’s 1 day work = `1/6`
X’s share for 1 day = `1/6 xx 48000` = ₹ 8000
X’s share for 3 days = 3 × 8000 = ₹ 24000
Y can complete the work in 8 days.
Y’s 1 day work = `1/8`
Y’s 1 day share = `1/8 xx 48000` = ₹ 6000
Y’s 3 days share = ₹ 6000 × 3 = ₹ 18000
(X + Y)’s 3 days share = ₹ 24000 + ₹ 18000 = ₹ 42000
Remaining money is Z’s share
∴ Z’s share = ₹ 48000 – ₹ 42000 = ₹ 6000
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?