प्रश्न

A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?

योग
Advertisements

उत्तर

A's 1-day work =`1/10`

B's 1-day work =`1/15`

(A + B)'s 1-day work =`1/10+1/15`

`=(3+2)/30=5/30`

`=1/6`

∴ Both A and B together can finish the work in = 6 days

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (E) | Q 1 | पृष्ठ १३३

संबंधित प्रश्न

A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×