प्रश्न
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
Advertisements
उत्तर
(A+B) can mow a field in = 56 days
(A+B+C) can mow a field in = 42 days
∴ (A+B)'s 1 day work =`1/56`
(A+B+C)'s 1 day work =`1/42`
C's 1 day work =`1/42-1/56`
`=(4-3)/168`
`=1/168` 
L.C.M. = 2 × 7 × 3 × 4 = 168
∴ C can do the work in = 168 days
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?