A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?

योग
Advertisements

उत्तर

A can finish a piece of work in = 15 days

B can finish a piece of work in = 10 days

∴ A's 1 day work =`1/15`

B's 1-day work =`1/10`

(A+B)'s 1-day work =`1/15+1/10`

`=(2+3)/30=5/30=1/6`

(A+B)'s 2 days work =`1/6xx2=1/3`

Remaining work which will be done by A alone

`=1-1/3=(3-1)/3=2/3`

∴ A can finish 1 work in = 15 days

A can finish `2/3` work in =`15xx2/3` days

`=30/3`days = 10 days

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (E) | Q 8 | पृष्ठ १३३

संबंधित प्रश्न

In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×