A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
Advertisements
उत्तर
A can finish a piece of work in = 15 days
B can finish a piece of work in = 10 days
∴ A's 1 day work =`1/15`
B's 1-day work =`1/10`
(A+B)'s 1-day work =`1/15+1/10`
`=(2+3)/30=5/30=1/6`
(A+B)'s 2 days work =`1/6xx2=1/3`
Remaining work which will be done by A alone
`=1-1/3=(3-1)/3=2/3`
∴ A can finish 1 work in = 15 days
A can finish `2/3` work in =`15xx2/3` days
`=30/3`days = 10 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?