A Can Do a Piece of Work in 24 Days, a and B Can Do It in 16 Days and A, B, and C in 10 2/3 Days. in How Many Days Can a and C Do It Working Together?

Advertisements
Advertisements

प्रश्न

A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?

योग
Advertisements

उत्तर

A can do a piece of work in = 24 days

(A+B) can do a piece of work in = 16 days

(A+B+C) can do a piece of work in

`=10 2/3`days = `32/3` days

∴ A's 1-day work =`1/24`

(A+B)'s 1 day work =`1/16`

(A+B+C)'s 1 day work =`3/32`

C's 1 day work =`3/32-1/16`

`=(3-2)/32=1/32`

(A+C)'s 1-day work =`1/24+1/32`

`=(4+3)/96=7/96`

∴ (A+C) can do the work in =`96/7` days

`=13 5/7` days

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (E) | Q 6 | पृष्ठ १३३

संबंधित प्रश्न

In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×