प्रश्न
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
Advertisements
उत्तर
A's one day's work =`1/10`
B's one day's work =`1/12`
C's one day's work =`1/15`
A, B and C's one day's work =`1/10+1/12+1/15`
`=(6+5+4)/60=15/60=1/4`
Let the work completed in x days
∴ A's 2 days work + B's (x − 3) days work + C's x days work = 1
`⇒2xx1/10+("x"-3)xx1/12+"x"xx1/15=1`
`⇒1/5+("x"-3)/12+"x"/15=1`
`(12+5"x"-15+4"x"=60)/60` ...(L.C.M of 5, 12, 15 = 60)
⇒ 9x = 60 − 12 + 15
⇒ 9x = 63
`⇒"x"=63/9=7`
∴ Work will last for 7 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?